Engineering specialists assisting São Paulo state prosecutors found R$133.2 million in unjustified costs across six emergency construction contracts worth R$175 million awarded to Ercan Construtora, G1 reported on November 9. Their assessments describe inflated quantities of materials and services in municipal projects commissioned without competitive tendering. São Paulo’s infrastructure department disputes allegations of irregularities and overbilling.
One 228-metre retaining project along the Pirajussara stream cost R$64.3 million, of which specialists questioned R$57.5 million, or 89%. Its budget included 248 tonnes of wire against an estimated requirement of 24 kilograms. Nearly 25,000 metres of foundation piles were budgeted where the engineering assessment calculated a need for about 2,400 metres. Infrastructure secretary Marcos Monteiro authorized the emergency contracts after municipal officials identified imminent accident risks.
The assessments form part of a broader investigation into emergency procurement. G1 reported that the municipal audit court had identified signs of irregularities in 90% of 53 contracts it examined; those proceedings still await judgment. The infrastructure department said its budgets followed an established cost schedule and qualified engineers had confirmed immediate structural dangers. It said it had not received formal notification of the prosecutors’ reports and would submit supporting documentation. Ercan did not respond to G1 before publication.
State legislator Antônio Donato has asked the municipal audit court to incorporate the engineering reports into its ongoing proceedings and open a special audit of the department’s contracts awarded without tendering. The findings put the quantities charged to taxpayers under scrutiny, alongside the justification for bypassing competitive procurement. They remain technical assessments within ongoing investigations, rather than final rulings establishing liability or determining whether money must be recovered.